Brief overview
We are equiping the quays with an electrical connection system (for plugging in ferries) and constructing the energy building required to power it. This project is part of our strategy to reduce emissions at the port of Caen-Ouistreham and to improve air quality.
Useful information
Contact(s)
contact@portsdenormandie.fr
Budget
The overall budget is €4.6M:
- Ports of Normandy : €3.5M
- Europe : €1.1M
Including a €370,000 loan from the Banque des Territoires.
Project schedule
Studies
2025
Site preparation
2026 (summer)
Start of works