A maintenance facility for the Calvados offshore wind farm

Brief overview

In 2019, Ports of Normandy expanded the port of Caen-Ouistreham by three hectares to enable EDF to set up its operation and maintenance base for the Calvados wind farm. This base was inaugurated in 2023. In the long term, it should employ about 100 people. The project is the culmination of several years of cooperation between the Calvados wind farm and Ports of Normandy teams, and is part of a key programme of investment (€28M) we have undertaken for the port.  

 

 An ambitious programme... 

... that aimed to achieve multiple goals. In addition to the pontoons reserved for the ships transporting operations and maintenance staff of the future offshore wind farm, the facility is intended to guarantee the economic future of the port thanks to a new guidance system for cargo vessels entering the west lock, but also to improve working conditions for port users and the reception of fishers and recreational sailors.  

 

 

Useful information
Base_maintenance_Budget

Budget

 

The €30.2 M were distributed as follows:    

  • The maintenance facility for the Calvados offshore wind farm: €9,3 M
  • Lock entrance guiding structure: €11,5 M
  • Outer harbour development works: €9,4 M

 

The overall budget has been co-funded by: 

  • Normandy Region Council: €11,78 M
  • Calvados Council: €2,82 M
  • Caen la Mer urban area: €0,4 M
  • Ports of Normandy: €7,68 M
  • CCI Caen Normandy: €2 M
  • EDF Renewables: €5,52 M (royalty fee)
Gallery
Construction de la base de maintenance
®Ports de Normandie
Construction de la base de maintenance
©Paco Lissillour Biplan
Construction de la base de maintenance
©Paco Lissillour Biplan
Base de maintenance éolien en mer à Ouistreham
©Ports de Normandie
Press release(s)
Project schedule
Start of work on the East mole extension
November 2019
End of work on the East mole extension
May 2020
Start of work on the construction of the maintenance base
November 2021
End of work on the maintenance base
December 2022
Entry into service of the maintenance base
April 2023